13.08.040 Sewer connection-Permit required.
A. No person(s) shall uncover, make any connections with or
opening into, use, alter or disturb any public sewer or appurtenance thereof
without first obtaining a written permit from the sewer superintendent or
designee. Such permit shall be issued to the applicant by the city upon forms
approved by the city for such purposes.
B. Each applicant must pay the appropriate fees as set forth
under the rate schedule. Such fees, including but not limited to a permit fee,
connection fee and plant investment fee, must be paid at least sixteen business
hours before such service is requested. Failure of the customer to provide
adequate notice to the sewer utility as provided by this chapter shall result in
the charging of an administrative fee as set forth under the rate
schedule.
1. City will issue or deny a connection permit within ten
days of payment receipt. If connection is denied payment will be
reimbursed.
2. If connection is not made within one hundred eighty days
of permit issuance, city will reassess fees paid and applicant will pay the
difference between the current rate and rate paid.
C. No sewer permit shall be issued unless the system to which
a connection is sought has been inspected by the city, approved for use and
formally accepted by the city. (Ord. 654 § 1(part),
2004)